§ 250.460. What are the requirements for conducting a well test?
128 words·~1 min read·
/us/cfr/t30/s§ 250.460·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
(a)If you intend to conduct a well test, you must include your projected plans for the test with your APD (form BSEE-0123) or in an Application for Permit to Modify
(APM)(form BSEE-0124). Your plans must include at least the following information:
(1)Estimated flowing and shut-in tubing pressures;
(2)Estimated flow rates and cumulative volumes;
(3)Time duration of flow, buildup, and drawdown periods;
(4)Description and rating of surface and subsurface test equipment;
(5)Schematic drawing, showing the layout of test equipment;
(6)Description of safety equipment, including gas detectors and fire-fighting equipment;
(7)Proposed methods to handle or transport produced fluids; and
(8)Description of the test procedures.
(b)You must give the District Manager at least 24-hours notice before starting a well test.